PROJECT NAME:  Will Crandall Reservoir Project - Construction Blog

   
 
Reservoir Rendition
   
 
   
 

The Crandall reservoir and its components are projected to be completed in spring 2014. Hillsboro Water will be keeping this project blog during that time so you can follow the construction process via words and pictures.  Updates will occur about once per week, or whenever significant or interesting events happen at the site.  Please feel free to e-mail us with any comments about the postings or the Crandall project. 

 

   
  May 8, 2013
   
 

Reservoir

DN Tanks is on the second week of wrapping the exterior of the reservoir with the 1st of 3 layers of 3/8” galvanized cable. A total of 80 miles of cable will be installed, with a layer of shotcrete (concrete slurry) sprayed over each layer, before the process is complete. Cable is stressed to 14,950 pounds to provide stability to the structure, primarily during earthquakes. The wrapping process is scheduled to be complete by the end of May.

Pump Station

The framing of the roof section is almost complete and the metal roof is soon to be installed. Interior electrical conduit and plumbing are being installed, and an 800kW back-up generator and switch gear have been installed for emergency operation. Interior painting and dry wall are next.   

 

Pump House Construction
Tank Wrapping
Pic Pump Station Pic Wrapping Tank

 

   
  April 5, 2013
   
 

Reservoir

On March 21st the contractor poured the final roof section on the structure. All concrete has now been completed, minus the main roof hatch and a couple of roof vents. The contractor is in the process of removing the interior roof shoring scaffolding and patching various holes and imperfections inside the tank. DYK, the subcontractor who will complete the exterior walls of the reservoir by wrapping them with multiple layers of tension cable and shotcrete, will mobilize onsite the week of April 15th to begin work.

Pump Station

The block wall mason has completed construction of the interior and exterior walls for the pump station and is in the process of mobilizing his material and equipment offsite. This week roof trusses will be delivered and work will begin on the building of the roof.

 

Reservoir Interior
Pump Station Work Continues
Reservoir Int Pic Pump Station Pic

 

   
  March 13, 2013
   
 

Reservoir

Last week, subcontractor DYK completed tendon pre-stressing in the walls of the reservoir. General Contractor, Ward Henshaw, is finalizing rebar placement and will pour the third of four roof slabs on March 14, 2013. The final roof pour will take place next week, weather permitting.

Pump Station

Masonry work is in full swing, especially considering the warmer, drier weather this month. Ward Henshaw lowered the water discharge pumps in place on March 13th, along with large piping pieces, prior to the structure being enclosed and only allowing limited access. Walls will be erected and completed in two weeks, then the roof trusses will be placed for roof construction.

 

Pipework
Roof with Rebar
Newly-poured Roof
picture pic pic

 

   
  February 26, 2013
   
 

Reservoir

The last of 18 reservoir wall sections were poured last week, along with the remaining interior concrete columns.

Earlier in the month, two of the four roof sections (north half) were poured. Crews are now moving shoring scaffolding and building forms for the south roof sections, with a concrete pour scheduled for the week of March 11th.

Pump Station

The floor slab was poured earlier this month and is two feet thick.  Now the contractor is preparing for the start of masonry work to construct the exterior walls for the building. The block wall will be completed in approximately three weeks.  After that, roof joists will be placed, and the roof will be installed.

 

 

Aerial 2-15-13

Aerial

 

   
  February 15, 2013
   
 

The Evergreen School STEM Club revisited the Crandall Reservoir and checked out the walls and roof that have been poured since their last visit.  Taylor Smith, a reporter from the Oregonian, also accompanied the group and wrote an article about the partnership:  http://bit.ly/Zgf7re

 

STEM students view groundwater pump
Evergreen students pose in front of crane
Partially-poured cover
Pic Groundwater Crane Pic Pic Roof walk

 

   
  January 10, 2013
   
 

Reservoir

Seventeen of the reservoir's 18 wall panels have been poured, and 62 of the 88 supporting columns have been poured. The contractor is now in the process of erecting roof shoring on the north half of the structure. There will be a total of four pie-shaped concrete pours to complete the roof of the reservoir.

Pump Station

The contractor finished the 24” ductile iron fill pipeline between the JWC 66” transmission pipeline tap and the pump station. The aggregate subgrade under the pump station has been brought up to grade. Now the contractor will begin installing utility conduit that will be used for housing several  electrical and communication cables that will service the building. Once the conduit is in place, the 24” floor slab will be poured.

 

Reservoir Walls
Reservoir Columns
Image Image

 

   
  December 10, 2012
   
 

Construction update on two elements of the Crandall Reservoir Site:

Reservoir

Ward Henshaw completed the last of nine reservoir floor slabs on November 27th, and is currently working on wall construction.  They have six wall sections poured and will pour four more this week.  The crews have also begun to pour the interior columns that will support the roof. As of Friday, December 7, they have poured eight columns and anticipate pouring a minimum of four columns each work day (There are 88 columns total).

Pump Station

Subgrade piping has been installed at the pump station, including the 24” inlet and outlet piping between the reservoir and pump station. Once the piping is installed, it is encased in concrete beneth the pump station floor. Other yard piping that has been completed includes the inlet fill piping with flow meter inlet and outlet vault and assembly.

 

Inlet and Outlet Piping
Piping
24 Web piping Pic

 

   
  November 7, 2012
   
 

Evergreen Middle School STEM Club Visits Resevoir Site

Students, interested in exploring future careers in the sciences, visited the newly-poured bottom of the Crandall Reservoir and felt the still-cooling concrete. 

 

STEM students learn about project.
STEM students tour reservoir site
STEM students stand on newly-poured reservoir bottom.
STEM Club pic Inside dig pic Reservoir hole pic

 

   
  October 3, 2012
   
 

Concrete Effort to form Tank Bottom

Today, Ward Henshaw completed the first of nine concrete pours for the base slab of the Crandall Reservoir.  This pour used approximately 250 cubic yards of concrete.  The total thickness of the base slab is 24 inches.” 

 

First pour for concrete base
Trucks deliver lots of concrete
Crew works together to create base
concrete pic crane pic pic
   
  September 14, 2012
   
 

Rock and Roll!

The subcontractor, Landis and Landis, has placed base aggregate and just finished installation of the underdrain piping and drain aggregate. Ward Henshaw is soon to begin forming for the concrete reservoir slab.

Excavation for the pump station piping and pump cans will begin next week.

 

View of Base Aggregate
Underdrain for Base Aggregate
Base Aggregate Pic Underdrain Pic

 

   
  August 30, 2012
   
 

That's one big hole in the ground!

Excavation for the reservoir is essentially complete!  This is the bottom!  From here on, the contractor will be going up.  Beginning next week, the contractor will be placing geotextile fabric and base rock for the tank.  The cement deep soil mixing (CDSM) matrix that will support the reservoir can easily be seen in these photos.

 

Aerial 8-28-12
 Top of Reservoir Hole
Aerial Big Hole

 

 

   
  August 7, 2012
   
 

Foundation core sampling completed

 

The cement deep soil mixing (CDSM) equipment can be seen at the top of the aerial photo dated July 12.  The CDSM contractor has been drilling core samples of the soil cement foundation for testing.  Now that the coring is nearly complete and the soil cement improvements have been accepted, the subcontractor performing that work is dismantling their equipment and removing it this week.  The final excavation of the reservoir to the bottom elevation by the civil construction subcontractor can proceed. 

Aerial

 

   
  July 20, 2012
   
 

Deep soil mixing finished.  Excavation accelerated.

The deep soil cement mixing has been completed.  The earthwork contractor is on an aggressive schedule to excavate the reservoir foundation.  The contractor is trying to get back on the original timeline after forced scheduling setbacks due to an extraordinarily wet spring. 

   
  July 12, 2012
   
 

Deep soil mixing nears completion.

The deep soil cement mixing is nearly complete at Crandall Reservoir site.  The subcontractor performing the work anticipates completion of the work next week.

What's up next?  The earthwork subcontractor will begin excavation to the bottom elevation of the reservoir foundation later this week.

   
  May 30, 2012
   
 

Construction Variance Notice

Ward Henshaw, Project Contractor, received a variance allowing extended construction hours (6:00 a.m.- 10:30 p.m., M - Sat), in order to expediate the deep soil mixing portion of the project.  The work variance will begin June 4th and will last for approximately two months.

   
  April 26, 2012
   
 

Equipment on site.  Test mixing to begin.  Noise issue addressed

Raito Inc. has moved onto the Crandall Reservoir site with a crane and the deep soil mixing equipment.  They plan to do some test mixing over the next month during normal working hours. 

Also, trucks bringing equipment to the site at 2 a.m. the other morning disrupted the sleeping neighborhood.  Hillsboro Water staff has asked the contractor to make sure that future equipment deliveries arrive during normal business hours to minimize noise impacts on the community.

   
  April 4, 2012
   
 

Crandall Reservoir site makes water connection - requires work in Evergreen roadway

The contractor is connecting to the waterline this week, which requires work in Evergreen Roadway.  The road will be open, but some traffic delays are expected. 

   
  March 27, 2012
   
 

Initial work on Will Crandall Reservoir site hampered by weather

Ward Henshaw has moved some equipment onto the Crandall site, and is busy creating the roads and construction area within the site.  Progress is slow-going due to the overly wet March weather, but such is spring in the Pacific Northwest.

 

   
 

March 14, 2012

   
 

Application for Exemption for Small Conduit Hydroelectric Facility

The City of Hillsboro Water Department is constructing a new 10 million gallon (MG) potable drinking water tank to increase storage capacity of the municipal water supply. As part of the proposed facility, a hydro-turbine has been designed to capture the excess pressure in the conduit between the 66” transmission pipeline and the tank. 

An application for exemption has been submitted to the Federal Energy Regulatory Commission (FERC) for approval. 

The application is available below for review. 

 

 
   
  March 5, 2012
   
 

Ward Henshaw Construction Company moving onto site

Ward Henshaw, project contractor, (PC) will mobilize and begin to move onto the Crandall Reservoir site today.  Once there, the first course of action will be to build a noise-mitigating berm around the site.

The PC received a variance that allows up to 90 days of extended construction hours (6:00 - 10:00 p.m., M-Sat), in order to expediate the deep soil mixing portion of the project. The berm, "Hollywood-style" generators and other techniques will be used to mitigate noise on site.

 

   
  March 2, 2012
   
 

Project Contact Information

Postcards were mailed out to site neighbors with contact phone numbers on them.  Hopefully, recipients will put the cards on their refrigerators, or in other handy spots, in case they need to call for information during the course of the project.  The numbers are also posted below.

Contacts are:

Contractor (Site Activity Inquiries):  503-519-7760

Hillsboro Water (Project Inquiries):  503-615-6702

 

   
 

Water •150 E Main Street • Hillsboro OR 97123 • (503) 615-6702 • Email


All Departments Administration Building Economic Development Engineering Fire Municipal Court Parks Planning Police Public Works Utility Billing Water more...
Administration Building Fire Library Municipal Court Planning Police Utility Billing