This project will construct a 36’ wide full street improvement along SE 18th Ave, from SE Oak St to SE Maple St. Improvements will include storm and sanitary replacements, curbs, sidewalks, and street lighting. This project will complete the collector route through this neighborhood, when combined with the Oak St, Maple St, and 21st Ave projects which were previously completed.
Doug Gresham
Project Engineer
503-681-6238
Send an email.
Current Activity – Contract in process of being awarded.
- Estimate completion date: October 31, 2010
- Design Start: April 25, 2010
- Bid Date: February 10, 2010
- Construction Completion: August 31, 2010
Note: Dates are subject to change due to weather and/or other unforeseeable events.
|
Public Works •150 E Main Street • Hillsboro OR 97123 • (503) 681-6147 • Email
|
|