The City of Hillsboro currently has jurisdiction of over 222 miles of roadway. The City will be hiring contractors to complete approximately 29.7 centerlane miles of annual maintenance in the form of crack sealing, slurry sealing, asphalt replacements (digouts), and overlays as part of this year's annual Pavement Management Program. Following the approval of the 2011-2012 budget and contract bid savings, the City was able to add 1.3 centerlane miles of overlays.
Teresa Gibson
Project Manager
503-681-6234
Send an email.
Current Activity – In Construction .
-
Project Development: November 2010 - May 2011
- Bid Date: May 19, 2011
- Award Date: June 21, 2011
- Construction Start: July 2011
- Completion Date: October 21, 2011
Note: Dates are subject to change due to weather and/or other unforeseeable events.
|